Installation :
The Kebao false floor installation is to be done with the company
recommended procedure through authorized dealer and
installation-contractor. The floor should be hard, level & free form
dust / moisture. Two coat of epoxy paint on the existing floor is
recommended. Do water level marking & pedestal marking at site prior
to installation to avoid overlapping of the services. Complete the
cable tray, piping, insulation, and control panel MS stands activity
before installing the access floor then lay the complete kebao
system including the tile, pedestal & stringer at one starch and
place the cut pieces of the tile, fix the pedestal using anchor
fastener or epoxy adhesive. Do the final leveling of the false floor
jamming the total system from all sides. Remove the center full
tiles for placing the cables & other services using panel lifter.
Tiles can be cut at site for wire opening & grommet fixing.
|
|